It is July 2010 and the Apple Valley building site is cooking. Outdoor temperature is 33 degrees and it is hot! The crews continue to make excellent progress. As of July 8, siding is beginning to appear on the building. The Drywall crews are working inside and much of the plumbing and electrical are now in place. The project remains on schedule. This picture shows the new siding on the eastern face of the building. 